Brockville – The City of Brockville will start Road Rehabilitation on various City streets in August and September. The top 40mm (1 ½”) of asphalt will be removed by a cold milling process and then replaced with new hot mix asphalt within the following couple of weeks.
- Expected Start Date: August 11th, 2025
- Expected End Date: September 19th, 2025
The timeline is subject to change pending weather conditions. Future notice to be provided if changes are necessary.
- King Street East: from North Augusta Road to the East City Limit
- Laurier Boulevard: from California Avenue to Broome Road
- Laurier Boulevard and California Avenue intersection
- James Street: from Park Street to Ormond Street
- Central Avenue: from Ormond Street, 70 metres east
- Ormond Street: from Central Avenue, 145 metres south
- Central Avenue and Ormond Street intersection
- Elm Street North: from Brock Street to the bridge
- Elm Street South: from the bridge to Abbott Street
- William Street: from Pearl Street to Brock Street (base of bridge)
- Stewart Boulevard: from north of the base of the bridge to Front Avenue
- Hill Street: from Pearl Street to James Street
- Kent Boulevard: from Parkedale Avenue to the Cul de Sac
- Millwood Avenue: from Morris Court to Liston Avenue
- Liston Avenue: from Milwood Avenue, 60 metres west
- Fairmont Drive: from Reynolds Drive to the Cul de Sac
- Hubbell Street: from Strowger Boulevard to the west city limit.
This work will be completed by G. Tackaberry & Sons Construction Co. Ltd.
Supervision of construction will be carried out by the City’s Engineering Division; Drew White will be the inspector on the site. He can be reached at 613-342-8772, extension 3224 or click here to email Drew White.
A degree of inconvenience and traffic disruption will be experienced, but we shall endeavour to keep this to a minimum and again suggest that you call us if you have any questions or concerns.
https://brockville.com/city-services/roads-sidewalks-traffic/



More Stories
Cataraqui Conservation Issues Flood Outlook Statement for Inland Lakes & Streams
Yellow Warning – Rainfall Issued for Brockville, Leeds-Grenville For Tonight Into Saturday
Good Evening, Brockville, Leeds-Grenville! Local Weather Update – Friday, March 6, 2026